Post Tender Process:
It is critical to note that the winning partici-
pant does not automatically qualify for a pre-license by the EMRA. It
is therefore required from the TEİAŞ and the winning participant to
take the following actions prior to the granting of the pre-license by the
EMRA:
• The results of the tender shall be submitted by the TEİAŞ to the
EMRA, including the official opinion received from TEİAŞ
concerning the connection to the grid;
• The TEİAŞ shall inform the EMRA of the companies that did
not participate in the tender and those participants that were
disqualified due to incomplete documentation, as well as the
highest Contribution Fee offered;
• The letter of guarantee of the tender participants that were not
granted pre-licenses shall be duly returned to the disqualified
participants;
• The letter of guarantee of the winning participant shall be
returned to the winning participant in the event thatthe pre-
license is rejected by EMRA due to force majeure or other rea-
sons deemed acceptable by EMRA. The letter of guarantee
shall be recorded as revenue once the winning participant fails
to fulfill its obligations under the Tender Regulations and/or
fails to execute the Contribution Agreement.
Contribution Fee Agreement
Following the official announcement of the results of the tender
and within 15 days of the receipt of the result of the tender by the win-
ning participant, the winning participant shall apply to the TEİAŞ to
execute the Contribution Agreement in the form attached to the
Invitation Letter.
The total contribution fee is calculated by multiplying the installed
capacity with the Contribution Fee proposed by each unit’s MW. The
total Contribution Fee may be paid in installments over a maximum
period of three years.
The letter of guarantee submitted by the winning participant for
the tender process shall be replaced by the winning participant with an
290