On March 25, 2020, the International Chamber of Commerce (“ICC”) published the new force majeure and hardship clauses: ICC Force Majeure and Hardship Clauses 2020[1] (“2020 Clauses”). The 2020 Clauses update the ICC Force Majeure and Hardship Clauses 2003 (“2003 Clauses”), offering a simpler presentation and expanded options to suit various companies’ needs[2].
The work on the update began with the creation of the short form (“Short Form”) of the ICC Force Majeure Clause 2003 (“FM Clause 2003”) to be directly incorporated into contracts. This was then followed by the revision of the FM Clause 2003, as well as the ICC Hardship Clause 2003 (“Hardship Clause 2003”), to accompany the Short Form. In the ICC Force Majeure Clause 2020 (“FM Clause 2020”) and the ICC Hardship Clause 2020 (“Hardship Clause 2020”), the language and mechanism are simplified.
The 2020 Clauses can be included in contracts, or incorporated by reference, by stating, “The ICC Force Majeure Clause (Long Form) / The ICC Hardship Clause is incorporated in the present contract.” The parties may also use these clauses as the basis for drafting a tailor-made clause, which takes into account their specific needs. Should the parties prefer a shorter clause for force majeure, they can include in their contract the Short Form. The FM Clause 2020, nevertheless, gives guidance on issues upon which the Short Form is silent.
FM Clause 2020
Structural Changes
In principle, the FM Clause 2020 follows the structure of the FM Clause 2003, while bringing certain novelties in terms of its structure. These novelties aim to create a user-friendly and easy-to-understand text, not only for lawyers, but for the parties, as well.
Whereas the FM Clause 2003 formerly only described force majeure, the FM Clause 2020 includes definitions of “Force Majeure” and “Affected Party”, as well as paragraph headings. “Force Majeure” is defined, as follows, in the first paragraph of the FM Clause 2020:
““Force Majeure” means the occurrence of an event or circumstance (“Force Majeure Event”) that prevents or impedes a party from performing one or more of its contractual obligations under the contract, if and to the extent that the party affected by the impediment (“the Affected Party”) proves:
- that such impediment is beyond its reasonable control; and
- that it could not reasonably have been foreseen at the time of the conclusion of the contract; and
- that the effects of the impediment could not reasonably have been avoided or overcome by the Affected Party.”
As another structural change, instead of the notes that are intended to comment on the provisions, the FM Clause 2020 includes explanations, if needed, after certain paragraphs to highlight various important points of that paragraph.
Main Conditions
As seen, above, the FM Clause 2020 retains the same conditions for the occurrence of force majeure, but makes some changes in the wording. In order for an event to be considered as force majeure, these three conditions must be established, together. There is no difference between the FM Clause 2003 and the FM Clause 2020 in establishing these conditions.
The FM Clause 2020 maintains the system introduced through the FM Clause 2003 for non-performance by third parties. This provision establishes its basis in Article 79(2) of the United Nations Convention on Contracts for the International Sale of Goods (“CISG”). The party invoking the force majeure must prove that the conditions set forth in the first paragraph of the FM Clause 2020 are established with respect to itself, and with respect to the third party.
Presumed Events of Force Majeure
Just like the FM Clause 2003, the FM Clause 2020 contains a list of events that are presumed to fulfil the conditions of being beyond the relevant party’s reasonable control, and reasonably unforeseeable. The working group that drafted the 2020 Clauses (“Working Group”), which I had the privilege to be part of, believed that inclusion of a list is more user-friendly and less complicated for SMEs, and provides predictability for users who are not accustomed to drafting these types of clauses in their contracts.
If any event listed is realized, the affected party is released from the obligation to prove that this event is beyond its reasonable control, and could not be reasonably foreseen at the time of conclusion of the contract. Therefore, the affected party must prove only that the effects of this event could not have been reasonably avoided or overcome. If an event is not listed, the party invoking such event as force majeure must establish all three conditions set forth in the first paragraph of the FM Clause 2020.
In the FM Clause 2020, the following events are not listed, contrary to the FM Clause 2003: Armed conflict or serious threat of the same (including, but not limited to hostile attack, blockade, military embargo), civil commotion or disorder, mob violence, act of civil disobedience, curfew restriction, and compulsory acquisition. On the other hand, taking the recent global developments into account, currency and trade restrictions, as well as embargos and sanctions, are now included on the list. Certain other changes and rewordings have also been made for simplification purposes.
For the sake of the principles of party autonomy and freedom of contract, the parties are allowed to add or delete events to and from the list, taking into account their particular needs.
Notification
In the FM Clause 2003, the notice requirement was not structured, independently, but was found within paragraphs 4, 5, 6 and 8 thereof. On the other hand, the FM Clause 2020 includes an explicit paragraph on the notification requirement. According to the newly added paragraph 4, the party affected by the impediment shall give notice of the event to the other party without delay.
Consequences of Force Majeure
The consequences of force majeure remain essentially the same as the FM Clause 2003, except for the changes noted, below:
- Under the FM Clause 2020, it is clearly provided that the non-invoking party is entitled to suspend the performance of its obligations, if applicable, from the date of the notice. It is an application of the well-established principle of exceptio non adimpleti contractus that finds its place in several national laws (see, for example, Article 97 of Turkish Code of Obligations No. 6098; Article 82 of the Swiss Code of Obligations; for sale contracts, Article 1612 of the French Civil Code; and Section 320 of the German Civil Code) and in Article 7.1.3 of the UNIDROIT Principles of International Commercial Contracts 2016 (“UNIDROIT Principles”).
- Whereas the FM Clause 2003 provided only a formula, instead of a fixed period for the moment at which temporary suspension of the contract through force majeure would last long enough to lead to termination; in order to increase certainty and foreseeability, in the FM Clause 2020, a maximum duration of 120 days has been provided, which can be changed by agreement of the parties at any time according to their needs. Accordingly, in addition to the general rule to determine each particular case as to when the duration of the impediment is unsustainable, the FM Clause 2020 suggests that, unless otherwise agreed, the contract may be terminated by either party if the duration of the impediment exceeds 120 days. By fixing a maximum duration, the Working Group added a new option to the formula exercised by Article 25 of the CISG, Section 8:103 of the Principles of European Contract Law, and Article 7.3.1 of the UNIDROIT Principles.
Short Form
The reason that led to creation of the Short Form is the fact that the FM Clause 2003 was preferred to be included in the contracts by way of reference, instead of full incorporation, due to its rather long and complex nature. The ICC Commercial Law and Practice Commission considered that reference to a clause outside of a contract is complicated and not user-friendly, and created the Short Form to be directly incorporated into contracts.
The Short Form comprises the main elements of the long form, but does so in only three paragraphs. In order to prevent any discrepancies between the FM Clause 2020 and the Short Form, both texts employ the exact wording. The Short Form does not have paragraph headings and explanatory boxes, and some paragraphs are unified. In addition, some paragraphs are not addressed in the Short Form, such as the non-performance by third parties, notification, duty to mitigate, and unjust enrichment.
Hardship Clause 2020
The main revisions in the 2020 Clauses relate to hardship. In the Hardship Clause 2003, only a termination option was available. Fear that the judge or arbitrator would adapt the contract in such a way that neither party would prefer played a role in shaping this drafting.
This time, the Working Group kept the first and second paragraphs of the Hardship Clause 2003 as is, but provided new options, such as adaptation of contract in the event of the parties’ failure to agree on alternative contractual terms. The Working Group believed that including an option for adaptation by a judge or arbitrator may act as an incentive for the parties to agree to alternative terms by themselves in order to avoid third party intervention.
Taking into consideration the global trend towards attempting to maintain the contract where possible (favor contractus), the Hardship Clause 2020 provides three alternatives: provided that the parties are unable to agree upon alternative contractual terms: (i) The party invoking the hardship clause may terminate the contract, but cannot request adaptation by the judge or arbitrator without the agreement of the other party (Option 3A); (ii) Either party may request the judge or arbitrator to adapt the contract with a view to restoring its equilibrium, or to terminate it, as appropriate (Option 3B); and (iii) Either party may request the judge or arbitrator to declare the termination of the contract (Option 3C).
- Option 3A is the same as the solution of the Hardship Clause 2003, which provides that the party invoking the hardship clause is entitled to terminate the contract.
- Option 3B provides for either party to request the judge or arbitrator to adapt or terminate the contract, as appropriate, as allowed for under various national laws, as well as the UNIDROIT Principles. An approach similar to that of the UNIDROIT Principles will prevent any possible discrepancies within the contract in terms of hardship situations.
- Option 3C is a modified version of the solution of the Hardship Clause 2003 and the new Option 3A. The Working Group considered that termination by the invoking party may be arbitrary and could be misused and, therefore, preferred to involve the judge or the arbitrator in the termination so that either can assess the burdensome conditions that may lead to termination of the contract, since termination should be the last resort.
Conclusion
The FM Clause 2020 mainly follows the FM Clause 2003 in substance, but with certain structural changes to make it simpler and more user-friendly. The most significant changes may be summarized, as follows: (i) Simplification of the list of presumed force majeure events; (ii) Separate paragraph for the notice requirement; (iii) Suspension of the performance by the non-affected party when the affected party invokes force majeure; and (iv) Fixing a time period of 120 days for the duration of the force majeure after which the contract may be terminated.
On the other hand, the Hardship Clause 2003 has gone through a fundamental change through introduction of the adaptation option, in addition to termination. The Working Group took into consideration the UNIDROIT Principles, as well as the recent developments in national laws, and agreed that including an option for adaptation or termination by a judge or arbitrator in the Hardship Clause 2020 could be an incentive for the parties to agree to alternative terms by themselves.
It should be noted that the 2020 Clauses do not abrogate the 2003 Clauses. The parties may continue to use the 2003 Clauses, and will be able to do so by making clear reference thereto.
[1] Clauses are available at https://iccwbo.org/content/uploads/sites/3/2020/03/icc-forcemajeure-hardship-clauses-march2020.pdf.
[2] Erdem, H. Ercüment: “Revision of the ICC Force Majeure and Hardship Clause”, Dossier XVII: Hardship and Force Majeure in International Commercial Contracts, Paris 2018, p. 121 ff. for detailed information on this subject.
All rights of this article are reserved. This article may not be used, reproduced, copied, published, distributed, or otherwise disseminated without quotation or Erdem & Erdem Law Firm's written consent. Any content created without citing the resource or Erdem & Erdem Law Firm’s written consent is regularly tracked, and legal action will be taken in case of violation.
Other Contents
The Turkish automobile and light commercial vehicle market left the 2000s behind with steadily rising sales figures and the 2010s with high and stable sales figures as well. In this period, the growth of the market was driven not only by high purchase power but also by easy access to credit and product diversity...
Turkish Commercial Code No. 6102 ("TCC") provides the right to exit from the company to the shareholders of limited liability companies and the right to squeeze out the shareholder from the company, unlike the structure of joint stock companies, with the exit and squeeze out institutions specially regulated for...
Turkish Commercial Code No. 6102 (“TCC”) preserves the rule that the board of directors shall manage and represent joint stock companies. The TCC regulates how the power of representation shall be exercised, the registration and announcement of the persons authorized to represent, the transfer of the...
Ordinary partnerships are regulated under Turkish Law between Articles 620 and 645 of the Turkish Code of Obligations No. 6098 (“TCO” or the “Code”). The Law defines an ordinary partnership contract as a contract where two or more persons undertake to combine their labour or property to achieve a common...
Merger and acquisition processes are one of the legal processes that most seriously affect the identities and legal status of companies. After the completion of legal, tax, financial and operational due diligence reports, the parties initiate the negotiation process in case they reach an agreement on proceeding with the...
A popular business model for expanding market reach and brand recognition worldwide is franchising. Despite being less common than distribution agreements in the form of mono-brand store agreements, franchising is another significant method for extending luxury brands' distribution networks. Luxury brands use...
In the decision dated 14.06.2022 and numbered 2019/149 E. 2022/894 K., the Court of Cassation General Assembly (“CCGA”) evaluated the theory of piercing the corporate veil in the context of the relationship between the guarantor and the borrowing company in a dispute arising from a loan agreement...
The European Union continues to be an important investment center for foreign investors. According to data from the European Commission's "Second Annual Report on the monitoring of foreign direct investment in the European Union", the European Union received €117 billion worth of foreign direct investment in...
Transfer of shares is arguably the first legal transaction that comes to mind among the legal transactions regarding the shares of a capital company, and the most common transaction in practice. However, the shares of a capital company may also be subject to various transactions, other than share purchase...
Law No. 6563 on the Regulation of Electronic Commerce (E-commerce Law or Law) has recently undergone a radical change in order to regulate the behavior of the players in the rapidly growing and developing e-commerce sector. The new regulations that came into force as of January 1, 2023 envisage important...
On 11 June 2021, the German Federal Parliament approved the German Supply Chain Due Diligence Act (Lieferkettensorgfaltsgesetz) (“Act”) which affects not only German entities but also their suppliers in foreign countries (including Turkish entities). The main focus of the Act, which entered into force on...
On 21 December 2007, the Federal Council approved the draft revision of the Swiss Code of Obligations, which also includes amendments to company law. On 28 November 2014, the Federal Council referred the draft revision for consultation. Following extensive discussions and a long enactment process, the...
The Turkish Commercial Code No. 6102 ("TCC") regulates maritime trade contracts under the fourth part of the fifth book of the Code. Among the types of contracts regulated in this section, the most frequently used contract in international maritime transport practice is the freight contract regulated under...
Prohibition on hidden income shifting is one of the most important issues that is broadly regulated under Capital Markets Law No. 6362 (“CML”). In conjunction with CML Article 21, which has a broader context than Article 15 of the abrogated Capital Markets Law No. 2499, another significant step has been taken...
As a result of developing commercial activities and large-scale investments, especially concluded in the fields of construction, energy and mining, companies are seeking to participate in these investments by uniting their powers and expertise to take advantage of financial opportunities together. This tendency...
The Turkish Commercial Code (“TCC” or “Law”) has enabled companies to apply different structural models and to implement new legal formations by including spin-off provisions to its Article 159 et seq. In accordance with the provisions of the law, companies may transfer a certain element, or elements, of their...
The International Federation of Consulting Engineers is a professional association established in 1913, known as the FIDIC (Fédération Internationale Des Ingénieurs-Counseils). Its members are duly elected from consultant-engineer associations of various countries, and membership to the association is...
Incoterms are a set of rules introduced by the International Chamber of Commerce (ICC) to explain the commercial terms that are widely used in international trade. The purpose of Incoterms rules is to facilitate and expedite international trade in a safe and secure manner...
The regulation applicable to all Turkish ports prepared by the Ministry of Transport, Maritime Affairs and Communications that entered into force after being published in the official gazette on October 31, 2012 (˝the Regulation˝), consolidates all the bylaws, regulations and instructions in a single Regulation...
As a rule, rights and obligations arising from an agreement have legal consequences only between the creditor and the debtor which are parties to the agreement. This principle is referred to as "privity of contract." In general, contracts for the benefit of third parties, where the fulfillment of an...
The rules of e-commerce, which grow and develop with the digitalizing world, are changing. E-commerce has become the driving force of the digital economy. However, considering the growth rate of e-commerce and the transformation it has undergone in a short time, it is obvious that some...
The dissolution of a company is a specific type of dissolution, which results in the cancellation of the legal personality which was gained by registration at incorporation. The specific proceeding which leads to the dissolution, and thus, the termination of a company upon the constitutive decision...
Companies in which shares or authority to manage is held by members of a family are considered to be “family businesses”. Family members can hold shares that control the company, as well as retain management authority. Having a family business means opportunity, security and income for...
Turkey ratified the Convention on the Contract for International Carriage of Goods by Road (“CMR”) in accordance with Act No. 3939 dated 7 December 1993, and the CMR entered into force in Turkey on 31 October 1995. In accordance with Article 1 / 1 of the CMR, the carriage of goods by road...
Ordinary partnerships are governed by Article 620 et seq. of the Turkish Code of Obligations No. 6098 (“TCO”). An ordinary partnership agreement is defined as an agreement whereby two or more persons undertake to join efforts and/or goods to reach a common goal...
The concept of disguised profit transfer in joint stock companies, in its broadest meaning, covers the transfer of company assets to related parties and may occur in different ways. This concept is regulated in detail under capital markets legislation...
Share subscription agreements, which are commonly encountered in start-up investments, set out the terms and conditions of an investor’s participation in a company as a shareholder by subscribing the new shares issued in a capital increase...
The electronic signature, which has the same legal consequences as wet signatures if it meets certain conditions, has taken its place in many legal systems and has enhanced commercial life. Although there are various types and applications in different legal systems...
INCOTERMS are a set of rules introduced by the International Chamber of Commerce (ICC) to explain the commercial terms that are widely used in international trade. The purpose of the Incoterms rules is to contribute to and facilitate the safe and swift conduct of international trade...